Building a brighter future for Miramichi
The construction of the Miramichi Wellness Multiplex is underway off Douglastown Boulevard. The facility will offer an 1860 seat arena, walking track, double gymnasium, 25m/6 lane competition pool, leisure pool as well as enhanced community spaces - all of which incorporate sustainable design features.
This exciting project, expected to open in the fall of 2026, is now progressing through procurement and early construction stages. Stay tuned as we continue to share updates on this development that is sure to benefit the community and create a vibrant hub for all to enjoy.
Ongoing activities
Procurement of various sub contractors and supply contracts
- more than 30 sub contractors and suppliers are anticipated
Site clearing, grading and preparation is complete
Building foundations and arena cast concrete walls
Pre-cast concrete bleachers under construction
Competition pool floor is poured and walls being formed
Underground plumbing and electrical services underway
Structural steel fabrication underway
Upgrading and installation of utility power supply
Upcoming activities
Installation of water and sanitary services anticipated to
commence in mid September
Competition and leisure pool basin construction
Pre-cast concrete bleachers installation in October
Structural steel installation beginning in October